Further Data centre Power maintenance 13th to 14th October - 1900hrs to 0700hrs

12 hours
Complete
Complete

The maintenance is now complete. Thanks for your patience.

Underway

The scheduled maintenance is now underway. We'll keep you updated on our progress.

Scheduled

The data centre is doing further works on the power infrastructure tonight. We have completed preliminary work to mitigate any potential issues; however, Equinix will be shutting down the old power infrastructure and transfering it to a new system.

One of our engineers will remain onsite during the maintenance window to address any unexpected issues.

DATE: 13-OCT-2026 - 14-OCT-2026

SPAN: 13-OCT-2026 - 14-OCT-2026

LOCAL: TUESDAY, 13 OCT 19:00 - WEDNESDAY, 14 OCT 07:00 UTC: TUESDAY, 13 OCT 18:00 - WEDNESDAY, 14 OCT 06:00

We apologise for any inconvenience this may cause.

Avatar for Stripe21 Support
Stripe21 Support
Affected components
  • S21 Voice Services
    • PBX Services
    • SIP Trunks
    • Voice Database Services
    • SBCs
    • Voice Radius Services
  • S21 Network Services
    • National Ethernet Services
    • Supplier Services
      • Voice Networks
      • Data Networks